Project information
Building: Data Centre
Location: Central London
Installer: FSS (Fuel Storage Solutions)
Project Completion: July 2013
Geberit Know-How
Project overview
A Data Centre in Central London required new bulk tanks, polishing systems and pipework, fully linking with the existing single skin welded steel pipe system. Tanks had to be drained and de-gassed, with temporary tanks installed and out of hours works required, making the project a particularly costly one.
Fuel Storage Solutions (FSS) historically used compression, single skin, stainless steel pipe on similar jobs, but this particular application required bunded pipe. FSS worked with Geberit in Germany to develop a suitable pipe, complete with a ten year warranty. FSS is now the only company in the world that can offer bunded press-fit pipe of this type and the only company approved by Geberit to fit it.