Cymmer Primary school
Project Information
Location: Rhondda Cynon Taf
Contractor: Allied Mechanical Engineering ltd
Project Completion: November 2018
Geberit Know-How
Problem: Major improvements needed to the junior section of Cymmer Primary School
Solution: Remodeling and refurbishment
Project Overview
Major improvements were made to the junior section of Cymmer Primary School in 2018, as part of a joint investment by Rhondda Cynon Taf Council and the Welsh Government’s 21st Century Schools Programme. The workswere carried out to improve provisions for pupils, and, in turn, improve educational outcomes.
The £1.9 million investment saw extensive remodeling and refurbishment work to the existing late Victorian-era building, 1960s building and multi-use games area.
Taking six months to complete, the internal work included the installation of 3,500m of Carbon Steel piping, electrical and mechanical works, and a change of layout forming some new rooms, toilets and a multi-purpose hall.